How Does Project and Resource Scheduling Software Work?

Summary

What are the processes that your project software goes through to produce a project plan? What information do you need to provide to enable it to work effectively? If your software can schedule resources as well, how does it do that and what data does it need?


Project (or Time) Analysis
Your scheduling software needs some basic data to be able to work out the schedule:
- The tasks in the project;
- How they are related - their dependencies;
- Their estimated durations, which may be calculated from the estimated effort.


You may also want to impose some constraints on the schedule, such as locked target dates (this task must start on or finish by this date, or cannot start before this date), or delays (lags) or overlaps between tasks.


Once it has this information, the software will start at the first task (the one which has no predecessors) and work its way forward through all the links, calculating the earliest start and finish dates for each one.


Having worked out the earliest dates, the software then starts from the last tasks (the ones with no successors) and calculates the latest start and finish dates for each task.


You can see that it makes sense if you can define a single start task and a single end task, otherwise the calculation is made more complex. These can be milestone tasks called Start Project and End Project, if you like, and help to make the whole network much neater. (A milestone task is one which has no duration.)


When all the dates are in place, the software can calculate the total float - the amount of time by which a task can be delayed without affecting the project end date. It may also calculate free float, which is the amount of time by which the task can be delayed such that its succeeding tasks can still start at their early start date.


The tasks which have no float are identified as critical, i.e. delays to these tasks will affect the project finish.

Resource Analysis
If you have limited resources, you may want the software to work out a schedule based on the availability of those resources. This implies that you need to do the following:


1 Estimate resource requirements
You may have already done this in order to calculate the durations of the tasks, in which case the requirement would be entered as the total effort. Alternatively, if you have specified the duration, you might enter it as so many hours per day or as a percentage of the resource's daily availability.


2 Allow tasks to slip
Float must be introduced into the whole schedule. You might do this by specifying a target end date on the last task which is considerably later than the calculated latest finish date. Or your software may allow you to specify by how much time the whole project can slip (may be called overrun).


3 Specify priorities
You might want certain projects, and tasks within projects, to take precedence when resources are allocated to them. There should be a way of indicating the priority at both project and task level.


4 Allow task splitting and/or variable durations
Your software may let you specify that certain tasks can be split to avoid overloading resources, and/or that the duration of the task can be extended. The minimum permitted duration of the split elements and the amount of time by which the duration can be varied should be specified.


With all these elements completed, the software will progressively schedule the tasks (according to priorities) later and later to avoid resource overloads using:
- Splitting and variable durations;
- Standard and variable durations plus float;
- Standard and variable durations plus overrun.


Even after using all these possibilities, there may still be some resource overloading.


Problems with Automatic Resource Scheduling
There are a two main issues associated with using the software to schedule tasks according to resource availability.
1 Project managers do not like their projects being rescheduled without their direct input.


They may prefer to use manual methods of rescheduling to avoid overloads.


2 A considerable amount of extra information on every task on every project is required to make the process work properly.


If your projects are planned at a very high level, e.g. only one or two tasks per project, then this may not be an onerous burden, but for many project managers the amount of time that would be spent setting up the data on a multitude of tasks in each project is not outweighed by the usefulness of the result.


Conclusion
Scheduling software can be very useful, but you need to know what data it needs to work effectively, and understand how much effort may be required to input that data.

About the Author:

Linda has a Master's Degree (with Distinction) in Technical Authorship, and over 25 years' experience in software implementation and consultancy. She was a member of the management buy-out team when 4c Systems Ltd was formed in 2002, having worked on the 4c product for 5 years before that.

Article Source: http://www.articlesbase.com/software-articles/how-does-project-and-resource-scheduling-software-work-539950.html

Author: Linda Russell

How to Choose Project Management Software

In today’s business environment everyone needs Project Management tools. And professionals who manage Projects are called Project Managers. Qualities to look for in a project manager are inspired and shared vision, good communication skills, Integrity, enthusiasm, competence, ability to delegate, handle pressure, and team building and problem solving skills.


Software related to Project Management is called Project Management Software. Professionals who manage teams, budgets, people, portfolio, cost, and last but not the least, time - need Project Management Software.

It is important for professionals that they learn to use Project Management Software as a priority so that they are able to build schedules quickly and efficiently and it will also enable them to update their projects on weekly, daily or fortnightly as needed. Updating status of the projects is trivial and usually does not take long. There are two types of project management software a) of the shelf like MS Project or custom made to suit individual business needs and there are several levels in project software based on technology or level of sophistication.

There is a wide range of choices available with different price tags attached. One must also understand the fact that merely using a Project Software does not make an executive more effective, it just makes them more effective. A professional should never be under a wrong impression that merely getting Project Management Software or project software will give them an edge automatically. Unless you’ve chosen the right software for your business and you are clear about your Project management skills, it won’t help. Poor project management and selection of project management software often leads to missed deadlines, cost overruns and sometimes-outright failure of the project.

Before you look at various kinds of Project Management Software available in the market, it is important to weigh it against your Project Management skills. This will help you choose the right tool for your business or profession. Project Software for managing small project will be different from Project Software that you will need to manage cross-functional projects for clients and executives. Likewise, managing a multi project environment will require a different type of
Project Software. Project Management skills should always be considered as important criteria while choosing Project Management Software.

Before choosing and installing Project Management Software it is also important that they are compared in all aspects. You should also check out Web-based project management software. This kind of Project Management Software enables information to be published instantly and can be made available in real-time, and changes dynamically as per the factors on the project that change.

Before getting Project Management Software for your organization, give it a good long thought. Learn about it and how can it help your business run more efficiently and whether you or your project managers possess the skill sets to operate it. If you don’t, do you plan to hire a project manager who can and can you afford one at this stage. All these considerations will help you in making an informed decision.

About the Author:

For more resources about Project Management or even about Project Software please review this web link http://www.i-ssis.com

Article Source: http://www.articlesbase.com/management-articles/how-to-choose-project-management-software-631417.html

Author: Groshan Fabiola

Perpetuum Software Launches .net Modelkit Suite 3.8

BARNAUL, Russia - May 12, 2008 - Perpetuum Software today announces the availability of .Net ModelKit Suite 3.8, a suite of four components that enable .NET developers to create BI applications for reporting, data processing and visualization. Tight integration between components of the suite ensures fluidity in every aspect of your workflow, providing similar design-time and runtime customization facilities, common data management and appearance customization. All suite components are written in C# and contain only 100% managed code.


The suite combines new versions of OLAP ModelKit™ and Report Sharp-Shooter™, the use-proven Business Intelligence components for intelligent data handling and feature-rich presentation. Another component is the Instrumentation ModelKit™ which is ideal for creating digital dashboards and KPI, offering an unmatched collection of over 130 ready-made gauges and other visual controls. Also included in .Net ModelKit Suite is the Chart ModelKit component which is designed for creating interactive charts and graphs. The components delivered in the suite minimize the coding required and provide full design-time customization.

Top 5 new benefits of .Net ModelKit Suite 3.8

The suite has been evolving over the last two years and has seen many technological improvements. The following is an overview of just some of the many exciting new features and benefits you'll find in the newest version of .Net ModelKit Suite.

#1: Work with the latest Microsoft tools - Experience a new level of performance and speed using the .Net ModelKit Suite components with Visual Studio 2008.

#2: Expand your reporting with new amazing abilities - Report Sharp-Shooter offers QR Barcode, which is very popular in Japan due to its efficient encoding of Kanji characters.

#3: Reduce time for templates development - Reports Sharp-Shooter offers master style support that eliminates the need to duplicate styles. Now, styles specified in the master report are available in sub reports, and they can be assigned to any report element. The unified style of master reports and sub reports makes your reporting system more professional.

# 4: Evaluate the product with new attractive samples - New to this version is a set of sample charts and gauges with attractive styles in Instrumentation ModelKit and Chart ModelKit.

#5: Enjoy efficient application development - The re-designed user interface in all designers and viewers, new icons on the toolbars make your application even more professional.

Please, explore www.perpetuumsoft.com to find out more information about the product. Some areas of note include detailed documentation for each component, demos and tutorials.

Pricing and availability

.Net ModelKit Suite 3.8 is available for $1600 (US). Customers may order directly from Perpetuum Software by visiting the Perpetuum store at www.perpetuumsoft.com. Registration allows the use of the components in projects on the royalty-free basis. Registered users get free one-year maintenance upgrades and technical support. A trial version of the product without functional or time limitations is available from www.perpetuumsoft.com.

About Perpetuum Software

Founded in 2002, Perpetuum Software LLC is a premier developer of Business Intelligence components compatible with .NET Framework and Visual Studio. Its flagship products include: Report Sharp-Shooter, .Net Dashboard Suite, Instrumentation ModelKit, Database Restyle, Chart ModelKit, OLAP ModelKit and .Net ModelKit Suite. The company is located in Barnaul, Russia. For more information, please call +7 3852 299979 or visit www.perpetuumsoft.com

About the Author:

Eugene Akinshin is a Ph.D., Chief Technical Evangelist for Perpetuum Software LLC (http://www.perpetuumsoft.com). He has 6+ experience in .NET and passionate supporter of new promising technologies.

Article Source: http://www.articlesbase.com/software-articles/perpetuum-software-launches-net-modelkit-suite-38-702269.html

Author: Perpetuum Software Team

Get Steel Detailing Solutions From Arjun Project Services

Benefit from the steel detailing services of Arjun Project Services






Steel detailing is a crucial part of any construction project where steel structure is used. Be it a large commercial construction, residential apartment, infrastructure development, steel detailing is important for flawless construction. With an effective steel detailing solution, there is always less chance of mistakes while fabricating the steel structures. With proper fabrication of the steel structure the construction is flawless. With meticulous planning of the steel structure and proper execution of the construction process, there is no chance of error in the construction. Therefore, there is hardly any need for rectification or reconstruction. So, it is quite evident that with an efficient steel detailer you not only get a flawless steel building but also save on cost and time involved in the construction process.





At Arjun Project Services, we are offering top quality steel detailing solutions based on the general drawings and instructions that we get from the steel fabricators. Our detailing solutions help the steel fabricators to effortlessly plan and construct the steel structure. We provide effective detailing service for the following steel structure requirements,





• Mechanical & Piping - Tanks & Vessels, Pressure Vessels, Piping Plan, 3D Modeling


• Civil & Structural - Steel Structures, Buildings, Industrial Sheds


• Electrical & Instrumentation - SLD, Load Calculations, Panels, PLC Logics





Along with detailing the structural framework solutions for steel structures, we also provide modeling & routing of piping for Petrochemical, Fertilizer, Power, Oil sectors & Gas Plants. [More]





At, Arjun Project Services, it has been always our sole aim to provide our clients with the best possible detailing solutions for their steel constructions. We have a team of 45 brilliant and experienced engineers, who work at our state of the art facility that is equipped with the latest computers and designing tools. We use cutting edge designing software solutions like the AutoCAD and Tekla X Steel that are the most recognized and widely used tools for designing steel structures. These are the most advanced and widely used constructional design and steel detailing software all round the globe. Our expert engineers make sure that you get absolutely flawless detailing solution that will effectively reduce your construction time and cost.





Contact Us


Arjun Project Services P Ltd


12, I Floor, I Cross St,


Karpagam Gardens, Adyar,


Chennai, India - 600020


Tel: + 91 44 426 666 77


Fax: + 91 44 421 151 74


Email: mail@aeg.co.in


About the Author:
Aeg.co.in offers steel detailing solutions, designed to help to reduce the hassles and cost of steel construction.

Article Source: http://www.articlesbase.com/technology-articles/get-steel-detailing-solutions-from-arjun-project-services-188875.html

Author: Arjun Project Services P Ltd

Software Companies Merge to Increase it Market Presence

The aim of this advantageous merger is to join technical and marketing expertise to offer extended services spectrum, more elegant and intelligent software solutions and products.

Enterra Inc. will be able to provide its customers’ projects with powerful and reliable software components for reporting, data analysis and visualization; it will dramatically reduce cost and timeline of customers’ projects and increase their ROI.



“Thanks to a large number of ready-to-use software components provided by Perpetuum Software we can cut down both the cost and the timeline for our clients’ projects”, stated Enterra’s CEO, Dmitry Starostenkov.



Perpetuum Software will intensify development of existing products; new releases will be announced oftener and will feature more new abilities. As usual all new and promising technologies will be delivered to the customers.



“Enlarged programmers staff will join experience and skills to work hard on new versions of the reporting and data visualization products we offer. I believe our customers will enjoy enhanced quality of our products and services”, said Eugene Akinshin, CTO at Perpetuum Software LLC.



So, customers of the combined company will benefit from this merger as they will get advanced software products, solutions and services of higher level. It will allow us to reach and address new market segments, as well as strengthen our position on the established markets.



Both organizations will go to the next stage of success, innovate and make breakthroughs in the IT industry.



About Perpetuum Software LLC (http://www.perpetuumsoft.com)


The company was founded in 2002. It offers .Net software components designed for reporting, data analysis and visualization. Company headquarter is based in Russia (Barnaul) with offices in Europe (Netherlands) and Latin America (Brazil). It stands as Microsoft Certified Partner. 3500 clients in more than 70 countries have been using Perpetuum Software products for 6 years.



About Enterra (http://www.enterra-inc.com)


The company was founded in 2001. This is a multi-national company with offices based in Tampa (USA), Walldorf (Germany), Barnaul, Moscow (Russia). Enterra specializes in custom software development, business systems integration, software products licensing. It stands as Microsoft Gold Certified Partner, IBM Business Partner, and Sun Partner. Its staff consists of over 50 highly professional specialists. For 7 years it has successfully accomplished over 300 projects.


About the Author:

Perpetuum Software LLC specializes in development of high-quality .NET and ASP.NET software components compatible with MS Visual Studio .NET, C# Builder, Delphi .NET and other IDEs supporting .NET Framework. Such use-proven components as Report Sharp-Shooter, Instrumentation ModelKit, OLAP ModelKit, Chart ModelKit, the .NET Dashboard Suite, OLAP + CHART ModelKit and other .NET components by Perpetuum Software LLC are already well known on the software development market and are used by developers in more than 60 countries.

Article Source: http://www.articlesbase.com/software-articles/software-companies-merge-to-increase-it-market-presence-618936.html

Author: Perpetuum Software Team

Selasa, 24 Maret 2009

Know What Colors Would Suit Your Home Project by Using Home Improvement Software

Colors play a very important role in your home improvement project. They widely express your nature and influence your mood. Deep and dark colors, for instance, depict deep and energetic feelings while light smooth colors develop a calm environment. But often times, you are confused about what color to choose. People don't know what colors would be best for their hallway, bedrooms, dinning rooms or bath and the kitchen. These are the people who ask for professional advice even when they have to paint their walls themselves.

This problem can be solved very easily with the help of home improvement software. It saves you the hassle to do and redo your home; and it brilliantly extends your visions. If someone has selected a color that doesn't seem to satisfy his mood, he will have to repaint his room with a new color and possibilities remain the same if the person is not very creative or if he has lack of experience. All this hassle will cost him a lot more than the budgets. Wastage of time is another related story. However, things are completely different when it comes to home improvement software.

With home improvement software, you can simply do wonders. You don't need any professional advice; you don't need anything else as well. All you are going to need is a piece of sharp brain and basic computer skills. From your bedroom to you kitchen and garage, take a preview of everything you want or do not want using home improvement software. One of the most acknowledged features of home improvement software is that you can adopt eclectic decor style and paint your room with different colors. If they suit you fine, get yourself working on them from out of your computer.

This software is simple in use and anyone can be able to decorate his/ her room, in fact, entire home with the help of this software. Besides being a magnificent tool for consumers, home improvement software has also been widely accredited among the contractors, builders, architects and designers. Because it's not just for colors, its uses are manifold. So, if you are planning any home improvements, get home improvement software in first chance.

For more about painting, designing, remodeling and everything that links together to result in a perfect home improvement, you can visit http://www.theyarelocal.com/articles/home_improvements/index.php

Article Source: http://EzineArticles.com/?expert=Aron_Joshua

By Aron Joshua

Causes Of Software Project Failure

Most software projects fail completely or partial failures because a small number of projects meet all their requirements. These requirements can be the cost, schedule, quality, or requirements objectives. According to many studies, failure rate of software projects is between 50% - 80%. This essay is a compilation of failure causes of software development projects; this essay summarises several areas that play a vital role in software project failure.

So, what really is the reason for software project failure? The sad fact is that software projects fail because we do not recognize that good engineering principles should be applied to software projects just as they are to building office buildings. We try to defend ourselves by saying that software construction is “different”.

One of the most serious complaints against software failure is the inability
to estimate with acceptable accuracy the cost, resources, and schedule necessary
for a software project. Conventional assessment methods have always produced
positive results which contribute to the too well-known cost infested and
schedule slippage.

Over the last 20 years many cost and schedule estimation techniques have been
used with mixed sensation due to restrictions of the assessment models. A major
part of the estimations failure can be due to a lack of understanding of the
software development process and the effect of that method used in the project
plan, schedule and cost estimates.

Failure Case Studies
Below are few of the case studies considered which will be analysed to fetch
the main reasons of failure of the software system.

Northumbria University developed accounting software to manage its day to day
business. The project could not come up with the desired results and failed to
meet the deadlines. Te investigations showed that the basic project management
procedures were not followed. This case study is referenced in this essay at
different points where necessary. [1]

Thai subsidiary (SMTL) of a Hong Kong-based multinational company (SMHK)
engaged in the manufacturing of electronic equipment. They implemented an
integrated software package; which was a failure at the several factors. These
factors were mostly management related. Such as a poor fit between the business
process assumptions inscribed in the software and the business processes in SMTL,
poor leadership at different levels, cultural differences, organizational
environment, and poor human resource management.

St John’s Hospital is a District General Hospital provides medical and
nursing services, which includes both general surgery and medicine.All these
services are supported by diagnostic imaging, laboratory, ambulance, pharmacy
and therapy services, which are all on site. As the major hospital in a tourist
area, it deals with many visitors in the holiday season, generating a large
amount of non-booked admissions work.

Software Management & Leadership
It has been shown repeatedly, that effective leadership is essential for successful IT implementation (Klenke, 1994). A leader must also have cultural sensitivity, communication skills, creativity, ability to delegate, and the ability to develop and retain human resources (Luthans, 1994). The software manager at (SMHK) was a western, where as the lower managers were Eastern. So there was a cultural clash going on always. Jack (Manager) always try to introduce creative thoughts. And most of the time the lower management could not do them. Hence there was a clash going on all the time.

Employees also felt that management hardly ever “listened” to their concerns
or attempted to address them. Consequently, many employees were eager to leave
the company, and did so as soon as they found alternate opportunities in other
companies.

Project Planning & Scheduling
Project planning means creating work breakdown, and then allocate responsibilities to the developers over time. Project planning consists of construction of various tasks, timelines and essential pathways including Gantt charts and PERT charts and different written plans for various situations.

It is quite usual in software development process to work backward from the
project end date which results in complete software project failure. It is
impossible that a project can be completed efficiently from the planning stage
to the implementation stage.

Allocation of roles and responsibilities has to be clearly defined, and it
becomes crucial while hiring the stall from outside. University’s higher
management failed to apply the basic project management rules which laid to the
project failure.

Proper scheduling is also required before the start of the project. It
includes the time scheduling, teams scheduling. Project managers don’t know what
they have to plan and schedule. They just only tell the programmer what to do
and the programmers can come up with a proper solution.

The development was moved to a new office and the office was not fully
equipped with the proper infrastructure. As time is also a big factor in success
or failure of a project. So it delayed the development process and contributed
towards the project failure. Infrastructure was not fully scheduled and
management team didn’t know where and how the project development will be
started.

The top secret of a winning software development project is to control the
quality up and lower the risk. Contingency plan is also the part of planning. In
case things went wrong then this plan can be followed to lower the affect of the
failure of project. Same was the case with university’s accounting software. The
management team had no such a contingency plan nor did they evaluate the risk
involved in the development of the new system. So it caused more trouble without
the backup system or backup plan.

The management just try to follow the methodologies like SDLC or RAD, but don’t know which methodology to use and at which time should apply the right technique.

Cost Estimation
Cost estimation is mainly involved the cost of effort to produce the software project. But it’s not limited to the effort only. It also includes the hardware and software cost, training the employees and customer, travelling to the customer, networking and communication costs. Cost estimation should be done as a part of the software process model.

Cost estimation needs to be done well before the start of the project
development. Failure of the budgeting for the cost of the project results in
complete disaster. As stated above the infrastructure cost, development tools
cost and hardware cost also needs to be estimated first.

Same thing happened to university’s accounting system development. They
purchased the new system well with out any serious estimation of the cost and
the income sources.

Below are the reasons why wrong cost estimation is done.

Inappropriate estimation methodology
Another reason would be the use of an inappropriate cost estimation methodology. Not a single methodology is better than other. Every methodology has its own strong and weak points which should be considered. Dr. Barry Boehm’s book Software Engineering Economics lists seven estimation methodologies. One or more of these methodologies can be used to estimate the cost of a project

“Good suggestion is that more than one software cost estimation methodology
should be used for accurate estimation”.

Cost estimation tools
There are many drawbacks in manual cost estimation. This technique is almost obsolete now. These days successful cost estimation includes the use of appropriate commercial software cost estimating tool.

Good software estimating tools do not always guarantee reliable software
estimates. Wrong input of the software size will result in wrong estimate.
Estimation software also needs to be customised for the specific need of
organization. These customisations require the data from the past projects as
input for the tool to estimate.

There are number of reasons these tools can return the wrong estimate.

Choosing the right estimation tool


Choice of a right estimation tool is necessary for the right estimation. The tool is not capable of handling the input and thus it can come up with the wrong estimate and hence cause the software project to fail.

Ease of customisation


As mentioned above the selected tool must be customisable according to the organisation needs, so that the organization can customise it according to the needs and past project data.

Easy to use and learn


The cost estimation tool should be easy to use and learn. It must include help and examples, simple and straight forward user interface. It must require less training to learn the system and inputs should be well defined.

Accurate Estimation


The estimation tool must have the capability to analyse all the parameters and come up with the accurate estimation for the cost.

Risk Management
Risk management is an important factor towards software project failure if it’s not managed timely and effectively. As nothing can be predicted that what will happen in future so we have to take the necessary steps in the present to take any uncertain situation in the future. Risk management means dealing with a concern before it becomes a crisis.

Risk Identification

According to the Universal risk Project there are two types of conditions which can be a symbol of as risk.

  • IF-THEN Statements
    • “IF technology is not available, THEN we will not meet the requirement”
    • “IF we cannot hire sufficient qualified software engineers, THEN we cannot meet the planned development schedule
  • CONDITION-CONSEQUENCE Statements
    • Given the “condition”, there is a likelihood that the “consequence” will occur
    • “Given that this specific test fails (the CONDITION), the CONSEQUENCE is that the planned schedule will slip”



Project managers have to identify the areas where the risk can be and how it
can affect the development of the project. Risk can be of technical nature or
non technical. Project managers needs to be aware of both the risks. Most of the
projects managers are not good in either of the side. A good manager with
programming skills can be good in identifying the technical risk but not in non
technical risk.

Risk Analysis
After the risk is identified there is a need to make the categories of that risk. Risk analysis is the process of examining the project results and deliverables after the risk analysis and applying the technique to lower the risk. After risk analysis is complete, the proper risk analysis plan needs to be made to cope with any uncertain situation. First identified risks are categorized and make the hierarchy of those risks. At this point the risk is classified as the positive or negative risks.

Risk Prioritization
After the risk is analyzed, the next step is to priorities the risk. At first focus on the most sever risk first; and les sever later. These risk factors can worked from time to time so that the final project out come is free of risk. So most of the time project management team fails to identify the sever risk and work on the less sever risk. This often results in the form of a crisis.

Risk Avoidance
Dealing with the risk is an art. Some times the management takes the projects with out identifying the proper risk involved in the project. So an experienced manager will take the project after proper risk analysis and avoid any risk involved in the project.

Risk control
Managing the risk to achieve the desired results and deliverables is done through controlling the risk at its best. This is a pure intuitive process and depends on the experience of the project management team, or risk already managed in past projects which were done by the same organization.

Conclusion
This essay has presented three basic factors which can cause the software development project to fail. Planning & Scheduling, cost estimation and risk management. All of these factors are to be considered at the management level and then transferred to the lower management.

Planning & Scheduling comes at first, good planning and scheduling makes the
strong foundation for the software project. Project planning consists of
construction of various tasks, timelines and essential pathways including Gantt
charts and PERT charts and different written plans for various situations. If
these factors are not taken into part then the software may encounter problems
during the development and the final product will be a failure.

Cost estimation depends on the budget of the project, customer type and the
size and effort to be put in the project. Cost estimations are done many times
during the life cycle of a project. It affects the project in many ways, wrong
estimation complete failure, affect the good-will of the organisation if the
costs are not covered, stake holders are affected and waste of resources.

Managing the risk is a practical approach for decreasing the ambiguity and
possible loss related with a software development project. Potential measures
can be considered as opportunity-focused (positive risk) if their consequences
are favourable, or as threat-focused (negative risk) if their consequences are
unfavourable.

[1]. infoNet is an Advisory Service funded by JISC retrieved on November 26 2006 from http://www.jiscinfonet.ac.uk/ Jones, Capers, Patterns of Software Systems Failure and Success, International Thompson Computer Press, Boston, Mass., 1996. Boehm, B.W., “Software Risk Management: Principles and Practices”, IEEE Software, January 1991 http://sunset.usc.edu/classes/cs510_2003/notes/risk.pdf “Software Risk Management: Back to Basics – The Top 10 (or so) Software Risks”, Software Technology Conference, 2003

Article Source: http://EzineArticles.com/?expert=Muhammad_Saqib

By Muhammad Saqib

Track Projects And Employees Easily With The Right Time Management Software

Critical for managers!

Project tracking, cost tracking and time management are critical areas for management. Managers need visibility into the activities of their employees and insight into where they stand with their projects. The best software programs will provide powerful Project Time and costing data in real time with a history overview for comparison so managers can be confident that their teams are producing at their full capacity.

Today's business environment demands managers operate their organizations leaner and smarter while becoming more cost effective. Informational insight is power and having a palate of over a hundred and thirty five customizable time and cost management reports available in a software program is the cutting edge of results.

Software Time Deployment

Time is a major factor when considering deployment of new software. A web-implemented software package means only a single installation on a main server and others access with a simple web URL. If your company is already tracking manually, it should be as simple as the importation of your existing data to save time or bringing over your existing data through integration with other software such as Microsoft Project, Microsoft Project Server and/or Intuit QuickBooks(Jobs, Tasks, Resources etc.).

Software Training

Do you think you are too busy for change? Many companies feel they are too busy to train their employees. Learning new software doesn't appear to be productive for your employees and can seem costly for your corporation. Finding the right software company that will stand behind their products and help with training can be daunting. However, that company is out there and the better you understand the advantages to your company, the faster you can make the right decision on your Time and Project Tracking software.

Project tracking, project time costing and project time management software will provide real time information to shape your team's production to full capacity. However, training should be easily implemented and user friendly in order to ensure employee adoption of the new software system. A program's adoptability rests in how easy it is to implement into your existing system with the least impact on business as usual. It is sometimes difficult to get employees to integrate a new system, but if a new software system ensures easy implementation and simple data entry they are more likely to adopt that system.

The company's management team and its employees need to access information in real time to make informed decisions and optimize productivity. Employees need the right software solutions that make their jobs easier to ensure solutions are adopted as part of their daily routine.

The right software for project tracking, cost tracking and time management, is the key to a company's productivity and of course their bottom line profits. Finding a software company that can deliver ease in transitioning from an old system to the new, cost effective system that will deliver big in tracking projects, ensures a smooth performance in operation.

Gregg Hall is an author living in Navarre Florida. Find more about this as well as time managment software at http://www.dovico.com

Article Source: http://EzineArticles.com/?expert=Gregg_Hall

By Gregg Hall Platinum Quality Author

How To Cut Business Costs With Employee Time Tracking Software

"Time" is the key word as it relates to money and software that saves and tracks time, increases efficiency and cuts project costs. Whether a company is small or an enterprise wide corporation, software that assists better time tracking, project time tracking and employee time tracking will ultimately increase your profits.

By reducing the time spent on time sheet data entry and project reporting, your organization will see cost reductions and productivity increases, which equals money saved. Understanding where each individual employee's time is spent and realigning that time as needed to best suit the needs of the current project is a major step toward greater profitability. Another important key to implementing great time management is the ability to move resources quickly between projects and tasks without effecting existing time entries.

The ability to access real time data on how any one or multiple employees' time is spent will allow you to make appropriate changes to reduce internal costs, realign project resources and time projections of project deliverables. Time is money! Time management and profitability are in direct correlation with how well time is managed and how well one can generate reports based on the numbers. This then reflects in the bottom line.

Having easy access to time management history allows your company to guesstimate (with accuracy) the man hours of a particular project, what that project will cost in labor and resources, the cost effectiveness of pricing, as well as effective quoting based on similar past projects.

Time tracking and project costing software applications should include time sheet software, time attendance software and time billing software in one easy to use graphic interface. Software designed for business intelligence reporting and including over 135 powerful reports and graphs in real time for time sheet management, performance management, project tracking, and project management will undoubtedly reduce waste of employee time and company resources.

DOVICO Software, which is compliant with DCAA, Sarbanes Oxley Act (SOX) and other quality control programs such as CMMI, COBIT and Six Sigma, will provide a software solution that delivers measurable results straight to the bottom line. This project tracking, project time costing and project time management software will provide real time informative data to shape your teams' production to full capacity. Training should always be easily implemented and user friendly in order to ensure employee adoption of the new software system.

A programs' adoptability rests in how easy it is to implement into your existing system with the least amount of impact on your business. The right software provides you with fast access to data, and should integrate with your existing software (example: Microsoft Project, QuickBooks & Active Directory).
The right software for tracking projects and employees easily increases a company's productivity and the bottom line. The right software will give your company better control of time and that is a statement of power.

Gregg Hall is an author living in Navarre Florida. Find more about this as well as time managment software at http://www.dovico.com

Article Source: http://EzineArticles.com/?expert=Gregg_Hall

By Gregg Hall Platinum Quality Author

Building Construction Software - Advancement in Building Construction Scenario

Building Construction Software is the software that is used to resolve and manage the building construction issues like cost of construction, the type of material used for construction, total budget and the time required to complete the construction project starting from zero up till its end. This software consists of multiple modules installed in it which helps at each and every step of the construction; from cost issue to selection of material to cost management problems. It helps in collecting the clients' requirements of the time to complete the project, the cost involved and the quality and standard of the material to be used for construction.

This software manages the record for the bids made for a certain project, billing agenda of the project, order status including accept, reject or update status. An important advantage of using this software is that all the records are maintained on a computer system, thus removing the need for paperwork and the fault of duplication of data. It also helps in making an estimate about the time and period required for the completion of a construction project. This software generates project specification reports of the cost estimates, transmittal, insurance of the project and also produces contracts that are to be signed and accepted between clients, contractors and suppliers of the construction material.

This software also efficiently collects the complex structural details of the projects from the data provided to it. There are six phases of using Building Construction Software which are:

1. Conceptual Design phase
2. Engineering phase
3. Detailing Design phase
4. Fabrication phase
5. Construction phase
6. Maintenance phase

The drawings and 3d models of the project are also generated by this software alone, hence eliminating the need of using different software. The Building Construction Software has opened new horizons for the builders, architects and contractors to take advantage from the latest software technologies.

Additional Resources

Construction Computer Software

Building Construction Software

Article Source: http://EzineArticles.com/?expert=George_Christodoulou


By George Christodoulou Platinum Quality Author

Senin, 23 Maret 2009

Using Project Management Software For Team Success

In today's dispersed work environments managing a project successfully take not only the right project management software it take the right team of workers managing the right resources. Lets face the facts: managing the the team is the most difficult function. To get and stay on the same page the team needs proper motivation. Managing and motivating is a complex skill on its own and it even more difficult when everyone works in dispersed locations.

Here are some tips

1. Analyze your own motivation for project management. List the positives in all situations. As a motivated project manager your team will have confidence in you and will follow willingly.

2. Make your team stakeholders. Describe to all how their individual tasks fit into the project. Explain why, any odd circumstances and restrictions surrounding the project.

3, Invite good suggestions from team members and when possible act quickly to show recognition. Act to fast implement the suggestion.

4. People usually work better virtually when the boss is not breathing down their neck. So use project management software to manage task deadlines but do it in a way that makes it a goal that the team can take pride in achieving.

5. Divide projects into clear milestones; good project managers motivate by defining attainable milestones within the project. Celebrate milestones completed on time.

6. Use words like WE instead of I. Don't brag about success

7. When problems arise take it to your team; when they understand the circumstances it is easier to motivate them to conquer the problem. Do not blame anyone in a team environment; it creates an environment of distrust.

8. Provide team feedback in a positive manner; tell them what was right, show them the shortcomings and how it can be done better. Ask for personal feedback on a positive manner.

9. Show your support for the team. When the going gets tough give them confidence and let them know you are there if they get stuck.

10. Have regular web conferences, listen to your team members talk and watch your team's body language. Let your team think "out side of the box" and encourage their participation for the good of the project.

11. Put the right resources together for the project. Not every team member can do every task. As project manager you pick the right person for task, provide the right tools and resource to met his task goal.

12. Ask yourself, "Which people work better with which people?" Grouping these resources into e-Teams for your project will lead to hire productivity and project satisfaction.

13. Channel issue reporting, use your project management software to notify virtual team members of problems. Miscommunications can lead to big problems. Resolve "situations" before they can damage the team (and personal) morale.

14. Give reasonable time lines for the task and then let the task responsible person execute. Insist that they use the project management software to enter their hours, notify the project manager of status changes. A good online project management software interface will help each team member keep current.

15. Reward appropriately when working with dispersed project team members. Not everyone needs the same benefits and kudos from a project. But remember to tell them that they did good work if you want to work with them again.

Using online software for controlling dispersed project management is the way to stay on the Same-Page

B Collen is the managing Partner for http://www.Same-Page.com He brings a unique perspective to this area due to his 7 years of experience helping companies with dispersed workgroups get on the same page

Article Source: http://EzineArticles.com/?expert=Brewster_Collen

By Brewster Collen

Project Management Professional PMP Exam Simulation Software

Many people looking to pass the PMP exam choose a software simulator and they are surprised at the results of there exam, compared to the amount of study effort. The software simulators are often tricky like the real exam. Some have complained that the PMP exam will try to trick you with the questioning and this can be frustrating. If you are using the PMP simulation program on a daily basis you will be able to see the patterns of tricks and you will be better prepared come exam day. With the timer added to the simulation software you will be able to use your time more wisely and you will be less likely to run out of time before you completed all the questions.

This can often be the difference between passing and failing the PMP exam. Even experienced program managers may feel compelled to select an incorrect answer and when the correct answer is given, they are often surprised. The often serves as motivation to learn and find the right answer. You can also combine different learning program because people have different styles of learning. You can read a PMP exam preparation book in conjunction with the software simulator. The answers in simulation program are often very detailed, explaining why the correct answer is right, helping you through the learning process. As you use this material, keep in mind that nothing can replace real expertise ad a project manager.

As you struggle with project deadlines, work around and with strong personalities, and decode the flow of the workplace you will gain a more intimate knowledge and mastery of what it's like to truly be a certified project manager.

Affordable PMP exam simulator, limited promotion, Pass the 1st time. http://www.pmsimulation.com

Article Source: http://EzineArticles.com/?expert=Joan_Williams

By Joan Williams

Project Management Software Or Excel - An Evaluation

"I just couldn't do without Excel!" This is something heard all over again when running project management software courses for account managers. Spreadsheets are used for calculating budgets, recording costs and income, calculating profitability by comparing both and much more. Even client facing documents, such as quotations and sales invoices are often prepared in spreadsheets rather than word processing applications putting up with reduced dtp functions in favor of the added mathematical features.

A spreadsheet has its uncontested benefits:

- one can work on it without being connected to a database or server
- it can easily be converted or integrated into word processing, presentation or internet files
- it is easy to link external files into it
- xls-formats are widely compatible, even to open source applications
- the user has complete flexibility to add functions, text and graphics into it

Exactly those points appear to be lacking from an integrated project management system:

- you need to be connected to a data base
- other applications cannot easily insert information from the data base
- there is no flexible linking of other applications into the data base
- the data base compatibility is restricted to the use of the same application or application language
- changes by the user to how the program itself works are restricted

When organisations introduce an integrated project management software one of the major hurdles to take in gaining user acceptance is therefore convincing users that this software cannot be compared to a spreadsheet program, it's a completely different kettle of fish.

However the apparent weak areas of project management systems are in fact their biggest strengths:

- as all users work in one data base, there is no time delay in sharing information and this information is always up-to-date. This addresses the challenge described by attendees of training courses of finding the latest figures and knowing if those figures are still correct when spreadsheets sit on local hard drives or in different server folders.
- because integrated project management systems have to produce forms and reports that meet auditing standards, these reports are tamper-proof documents ready and secure to be sent out to clients or suppliers. (On the job reporting side there are usually simple ways to get data out into spreadsheet readable formats that can then be processed further.)
- as data has to be entered into the project management software rather than automatically linked into it from external files, there is an extra level of data verification.
- From an auditing point of view the lack of backdoors into the data base using other applications than the integrated software increases the data security for the company
- Because calculations are part of the program, there is no danger of user mistakes. (On several occasions, when as part of training courses budgets or invoices were entered into a project management system to mirror information hitherto generated and held in a spreadsheet, totals didn't agree and the first suspect was of course the new software. Only when using a calculator double-checking the information it turned out to be right and the original documents or xls files had faulty formulas or broken links, which nobody had noticed before.)

The biggest advantage is of course that there is no further step required to get data into a financial system if integrated project management software is used.

So the résumé to the title has to not be "Project Management Software or Excel" but "Project Management Software for Project Management purposes and Excel for Spreadsheet purposes", where each is best in.

* Or an equivalent spreadsheet system such as "Calc".

Volker Bendel is manager of the training department of Agency Software Worldwide, the producers of the "Paprika/Rebus" job costing software (http://www.paprika-software.com) and (http://www.rebus-software.com). Originally from a legal background, he has several years experience in planning and implementing Job Costing and Accounting Software Systems in the Creative Industry. He has also delivered training courses in the UK, Europe, Dubai, the US, China and Australia. Prior to that he worked as a senior business consultant in Hong Kong and as a department manager of a design department in Hong Kong

Article Source: http://EzineArticles.com/?expert=Volker_Bendel

By Volker Bendel

Technical Writing - A Checklist For a Software Document Writing Project

Here is a general check list that you might find useful to make sure your software documentation project does not miss anything:

-Do you have access to the software project's Scope Document?
-Do you have access to the functional and marketing specs of the software project?
-Have you written a Documentation Plan for this project?
-Is your Documentation Plan approved by the client or the authorized project manager?
-Do you know who will review the document?
-Do you have an approved Template for this project?
-Do you know where you'll get your image and/or multi-media files from?
-Do you have an official Style Guideline that you'll follow?
-Will there be any single-sourced collaterals (like a help file, or a different-sized version of the same document) compiled from the same source file?
-Will you need any hardware to complete the project?
-Will you need to travel to other locations to gather information for the project?
-Will you need to interview any Subject Matter Experts to complete the project?
-Will you need to participate in or arrange any teleconferences or webinars to gather information or report about the project?
-What version management platform will you use for document version control? (MS SourceSafe? Agile?)
-How will you backup your files?
-Will you write the document alone or will there be other technical writers on the project?
-Will there be any in-house peer review required before you submit the document to official management review?
-Will the end product be localized and translated to other languages?
-Do you need to follow any special guidelines for localization?
-Will you have any access to a tracker system to incorporate the results of bug reports?
-Will you need to compile any training materials/sets from the source files?

If you take the necessary measures and precautions ahead of time depending on the answers to these questions you'll have a more successful documentation performance.

If you are interested to read more about what technical writing is all about and how it can help you earn a steady living, visit http://www.learntechnicalwriting.com. You might be pleasantly surprised with what you'll find out. Join the thousands who are already helped and inspired by this information provided by a Fortune 500 Senior Technical Writer. Visit today and claim your free report "How Much Do Technical Writers Make?"

Article Source: http://EzineArticles.com/?expert=Ugur_Akinci

By Ugur Akinci Platinum Quality Author

Drawing Management - What You Need to Know

Engineering projects are often unique to other projects because of the complexity in managing engineering drawings.

Most engineering projects have similar challenges which need to be addressed:

1) Gathering of initial data and information
2) Managing the information throughout the project life cycle
3) Distribution of information during and prior to completion of the project.

Gathering Project Information

When it comes to managing project documents most companies have a system for storing and retrieving information regardless of if they are using software. The common method for organizing information absent the use of software is storing files in a directory and logging data into a database or spreadsheet.

If you are storing files in a directory without the use of software, then the naming nomenclature for these files must be perfect. If a file is misfiled and the name is incorrect, it may never be located again. To track the drawing, the electronic file is often represented by a row of data in a spreadsheet or database which may include the drawing number, project name, creation date, etc.

A major factor in the gathering of project information is weather you have control over the manner in which the data is delivered to your project managers. If all of your work is prepared internally, then you have complete control. Unfortunately, this is usually not the case. If you have data that coming in from outside of your organization, can you influence the format that this data is presented in? You may get information delivered on a CD. You may receive data from e-mail or FTP, or a number of other delivery methods. The companies that receive data from multiple contractors via multiple methods have a big job in organizing this information into usable format.

A simple spreadsheet with 10-20 required data fields can reduce your work on the front end monumentally. If software is used, you may be able to import this information automatically and eliminate 90% of the work on the front-end.

Managing the Life-Cycle

The most complex part of managing project drawings and documents is in the lifecycle. During the lifecycle of project documents, they may undergo multiple changes, distribution, and collaboration between many parties. Companies who employ manual management of documents and drawings during the lifecycle must ensure adequate training and diligent execution of policies to ensure that mistakes are kept to a minimum. Certain aspects of project management are impossible to achieve without software. These include but are not limited to unauthorized distribution and a full audit history.

Tasks which are included in the life-cycle process are editing documents, collaboration on those documents, and approval of the changes. The challenge of IT departments is controlling who has access to these files and what kind of access each user has. With manual management, IT must set folder security for every folder in a project by adding a user to the security profile. If a user copies the file to their local drive, then the file on the server can be accessed by other users and work can eventually be overwritten. Companies can employee manual methods to prevent this problem from occurring. One method is to require the users to fill in a spreadsheet which notifies all other users that they currently have ownership of the document and no-one else can edit it at this time. In this case, all users must check the spreadsheet to make sure a file is available.

DMS software will manage a user's security access and his project memberships. Profiles and users can be changed easily so if workers change from project to project, DMS software will allow non-IT personnel like a Project Manager to administer security efficiently. Software will also allow a user with the proper security to search for a file on metadata or content in the body of the document, and then check out that document. Many engineering clients who use software restrict the engineers from accessing the actual file, but the engineer can however click a button which will convert the file to a PDF and allow her/him to save the un-editable version to the local hard drive.

During the lifecycle stage the drawings may be marked up by paper and pen and delivered to the designer by e-mail or hardcopy. The collaboration of information leading to a final version may include team members that are not residing at your physical location. In this case, some plans are delivered via UPS or FedEx. If software is used, members may download a PDF and markup in Adobe, or log into the DMS software and markup the drawing via a web browser. If a web browser is used, markups can be seen in a matter of seconds from anywhere in the world.

The next step in the lifecycle is to review the changes and approve or disapprove them. Once the designer has implemented all of the changes to the drawing or document, he/she will submit the document to the proper team members for approval. In some organizations this may be a single person and the communication may be as simple as an e-mail stating that the change is approved. If multiple members are involved in approving a drawing, then the process can be complex in managing comments from multiple members as well as making decisions about whose comments take precedence. Another factor to consider in the revision and approval process is the audit trail. When you need to find out why, when, and by whom a change was made; is that information available?

The last step in the lifecycle portion of management is the official revising of the document or drawing. In a manual process, the designer will copy the document, change the filename, and place the old copy in back-up location. DMS software will do basically the same thing automatically and without allowing for human error.

The release of the wrong drawing or drawing package can result in thousands to millions of lost revenue. When documents are submitted and distributed in a mixed array of methods, it can be very difficult to keep track of which is the latest version.

Distribution of Project Documents

Lastly, the project documents usually have to be distributed in some manner to external recipients. The important considerations here are:

1) Do the distributed documents need be tracked for future reference?
2) Will the documents be distributed in the native format or in non-editable versions?
3) What method of distribution will be used?

Document transmittals often include a specific "tracking number" which can be used to follow a specific group of documents which are distributed to a specific recipient. It is important to be able to prove to the recipient which versions were distributed at a later date if asked. If the transmittal process is occurring manually, a worker will log each document's relevant data into a spreadsheet including at least the document name, revision, recipient, and date.

Another very time consuming task of transmittals is the conversion of documents if this step is required. Most organizations cringe at the thought of distributing native CAD drawings that may be edited by someone who is not authorized. A transmittal which includes hundreds of documents and drawings may require a full days worth of work if conversion is manual. DMS software will automatically convert the project files, create a cover sheet of included documents, and automatically record the transmittal history for future reference.

Once the transmittal is ready, organizations may transmit the actual drawings via e-mail, FTP, or a web portal. If the size of the transmittal small, e-mail is the method of choice. E-mail is easy but it does not allow for tracking of activity or confirmation of receipt. FTP is a common method and organizations usually posses the internal expertise within their IT departments to manage this process without using expensive software. The most efficient way of communicating and tracking transmittals is via a web portal. The web portal can be posted via DMS software or SharePoint, or a combination of the two. Posting transmittals on a web portal can be most beneficial if feedback and collaboration are required and you want to assign a deadline. Recipients can even be assigned the ability to collaborate and post information to the project via the portal.

Summary

All of the processes outlined can be managed effectively with or without software applications. Logically, the necessity for automation in any of these procedures outlined depends on the volume of processing taking place at each step. As organizations expand, they will inevitably begin using automation and it is critical to get the manual processes organized first. Automation may eliminate some of the manual steps, but you cannot effectively achieve automation unless you can outline your steps.

Bret Lawson is a document management consultant with Practical Programs, Inc in Houston, TX. Practical Programs specializes in electronic document management for companies who use CAD files and associated documents. http://www.practicalprograms.net

Article Source: http://EzineArticles.com/?expert=Bret_Lawson

By Bret Lawson

Jumat, 20 Maret 2009

Event Planning Software: A Beginners Guide to Project Tracking

When using your event planning software, undoubtedly you reach the point where you need to perform project tracking. Depending on the size of the event, you will have one or more projects to accomplish prior to the big event.

Your event planning software should at least allow you to do the following two tasks:

Label the days of your project. You must have the ability to label each day of the week according to your project estimate. In other words, each day you estimate in your project timeline will have the name of the project attached to it.

Make notation about the details of the project on a daily basis. Your projects will have unique characteristics and challenges on a daily basis; so, you should be able to notate your project on each day. In your event planning software, you will be able to review roadblocks to your project and you will be able to see successful activities that have assisted your project moving forward. You will be able to notate specific techniques that have been instrumental in overcoming unique challenges.

As you can see, there are some particular features that must be in your event planning software that will allow you to properly assess your project at any one time. You saw that you must be able to associate the days of your project estimate to the actual name of your project. Additionally, you must be able to notate details of your project on a daily basis. You should be able to notate your successful techniques and the challenges you face along with the notable successes you experience.

(c) Copyright 2005 Olan Butler All Rights Reserved

Olan Butler is the Chief Architect of BHO Technologists, a computer productivity & organization software and service provider http://www.bhotechnologists.com with headquarters in Kansas City. His works also include the Appointment Calendar Software Store and the Kansas City Computer Repair Site

Article Source: http://EzineArticles.com/?expert=Olan_Butler

By Olan Butler Platinum Quality Author

What Does an IT Project Manager Do?

If you looked at the most prominent job searching website in your region you would find that different industries mean different things when they use the word project manager. For our purposes, we are going to talk about a typical project manager within the software development industry. By no means is this an exhaustive treatment of their duties and chances are good that no single person in a company would undertake all the tasks described here.

Before we can say what a project manager does, we should first take some time to define what a project actually is. We know that a project is often a novel undertaking, an attempt to create or achieve something which hasn't been done before (hence why projects are inherently risky). The other identifying features of a project include; they have a deadline, a set budget, and a beginning and end point.

A project can be broken into a number of components; design, programming, project management, quality control, etc. These are just the titles I use, but they do have direct parallels with traditional waterfall model stages (e.g. programming = implementation, quality control = testing, etc). For simplicity, I usually roll requirements gathering and system analysis into the project management component. I tend to refer to components rather then phases or stages. The reason for this is because it's limiting to try and force a software development project into a series of linear steps. It just doesn't turn out that way because there is so much iteration and overlap between stages (e.g. project management is a process that occurs the whole way through a project).

To get a project done you obviously need people with specialized skills, these people are often geographically distributed, whether that's down the hall from each other, or on another continent. The chances of these people coming together as an organized group is pretty slim. And this is where a project manager comes onto the scene.

So then, what is a project manager? You could say they are the glue that binds things together, they don't actually do the work, but rather help others do it. They are at the helm of a ship, steering it via a predefined route to a particular destination, with course corrections to be expected along the way.

Sure, this is a somewhat simplistic definition, but we are just getting started. If we were to expand on our description, we could also say a project manager is meant to make the unpredictable predictable, ensure resources are used wisely, and handle problems which seem to appear out of nowhere.

The purpose of software is to solve a business problem or exploit an opportunity. Based on this goal, a project manager is likely to assist in figuring out what features the application should have. Before a project begins in earnest, they also have to determined if the project is technically feasible and not prohibitively expensive.

A project manager should know about the people on his team and what their capabilities are. Who's good at JavaScript? Who knows about video encoding technology? Who's the best person to research a shopping cart component? This isn't just a matter of utilizing peoples' strengths, but also making them happy by allowing them to do what they like. For example, creating a timesheet template may be hell for one person, but sheer joy for another.

Setting up the ground rules for communication is also the domain of a project manager; is the team going to have regular meetings or impromptu chats? Are we using MSN or Skype to talk to our overseas contractors? How often will programmers report their progress so the project schedule can be kept up-to-date?

Scheduling is arguably the most important task a project manager undertakes. He needs to know if there are any dependencies (e.g. an Internet Merchant Account has to be setup before credit card payments can be accepted on a website). They need to be aware of any external factors affecting the project's deadline (e.g. the client wants to show off the software at a trade-show in two months). Regardless of what tool is used, the project schedule needs to at least say what is going to be done by when, how much time tasks will take, and who is doing what.

Resource allocation is a juggling act project managers need to excel at. Which programmer should work on what? When can they work on the next project? How much time should be set aside for bug fixing? Often companies will have multiple projects running simultaneously. This makes it quite tricky to get the most out of the limited resources available.

Making sure that the software solution delivered to the client is bug free and in fact what they asked for is another major responsibility of a project manager. This could involve writing tests plans, creating quality assurance standards, defining acceptance criteria, and organizing independent testers to carry out testing. A project manager is often the first person a client contacts when they find a bug in their software, ideally the client should be logging defects in a bug tracking system. The project manager then assigns the logged bugs to the most appropriate programmer for resolution.

A project manager is responsible for risk management. They need to be aware of what can go wrong and how likely it is to occur. Finding out about it after it happens is too late, a good project manager will spot a problem coming from a mile away and have a plan ready for dealing with it.

A project manager might need to consider external factors like: competition, industry standards, future market forces, environmental issues, social and political impact. It's quite rare for a project manager to be called upon to analyze and document these forces (e.g. they may do this as part of an e-strategy). Most of the time this information would be in the client's business plan.

At smaller companies it's not unusual for a project manager to wear a number of different hats. For instance, they will commonly double as a business analyst, responsible for writing functional specifications, creating wireframes, making recommendations on technology, and deciding what development tools to use. They may even have minor administrative duties like preparing invoices for clients.

Louis Marshall, Project Manager
My tech blog: pm4web.blogspot.com

Article Source: http://EzineArticles.com/?expert=Louis_Marshall


By Louis Marshall

Internet Hosted Time Tracking, Billing, and Project Management Software

Internet hosted time tracking, billing, and project management software must include easy access, secured data centers, customized interfaces, and integration capabilities. Without these subtle features, a professional may have issues providing the best service to clients. The features of well-designed software can increase billable hours and a professional's profitability.

Professional service firms find internet hosted software a reliable alternative to previous tracking methods. The software encourages new technologies which creates instant notifications of email, tasks updates, and billable hours. These additional resources provide service providers and clients with an outlet to reconfirm tasks effectively. With Wi-Fi accessibility in various locations, professionals can complete assignments on-the-go without worrying about accounting matters. The software notifies all parties and makes work easier to perform.

Ease of Access

Service professionals and firms need easy-to-access software for their work. The complications of accessing data reduce productivity levels and causes issues for many professionals. With an easy-to-access time tracking software available, professionals can track projects and update reports without frustration. The smooth transition of task management and billing enhances a professional's workflow once they access an interface. Strict confidentiality is offered by the software's secured data centers.

Secured Data Centers

In the event of an internet error or disconnection, the professional's information is backed up automatically on a secured data server. This feature is an incredible asset for professional team members in foreign locations. Client information is protected by a 128bit SSL Certificate which disables interceptors during working hours. Internet host of the software want professionals to work in a protected, reliable interface for the best results of their projects.

Customizable Interfaces

Legal professionals, IT consultants, and service team firms can customize their interfaces to suit their organization's procedures. Billing and invoicing is coordinated with the client's billing arrangements; an ease of comfort for professionals managing various aspects of a project. The internet hosted time tracking, billing, and project management software offers project tasks overview and integration capabilities as well.

Project Tasks Overview

The project tasks overviews inform team members, professionals, and clients of a project's status. This keeps all parties in sync with developments in progress. The internet hosted software acts as a sounding board for service professionals to understand their business' financial data as well. The tracking features are embedded for easy reporting of each project task making the work and billing easier in every direction.

Integration Capabilities

The internet hosted time tracking, billing, and project management software allows integration of account software such as PeachTree Accounting, QuickBooks, Lotus Notes, and more. No matter what the additional needs exists for companies, the software is customizable and easily adapted for their firms. These features ensure consistent accountability of project billable tasks.

The decision to implement efficient and secure internet hosted software removes barriers from professional financial issues. By customizing one's software, an individual can produce reports when needed and bill clients systematically.

With the efforts of high-tech software such as TimeSolv available, professionals can focus on work

For further information, please visit Internet Hosted Time Tracking Solutions

Article Source: http://EzineArticles.com/?expert=Hayi_Mansoor


By Hayi Mansoor Platinum Quality Author

Integrated Project Management Software - Issues With Localisation (Part II)

Having a fully integrated job costing and accounting system, that works perfectly in one country, should make it relatively straightforward to employ it in other countries as well. After all most modern operating systems are able to provide a more or less seamless international and multilingual functionality on the touch of a few buttons.

In particular for a multinational company having easy access to all of their systems across borders is an important aspect of management. The mere translation of the project management interface is indeed quite an easy part of the localisation as most languages have words for "project" or "sales invoice" etc. There are however two main issues that will arise, one due to the integration of accounting and one due to the multilingual interoperability of the system: This second part of the article will look at the multilingual accessibility and interoperability issues after the accounting and bookkeeping issues have been looked at in Part I, published earlier on this forum:

These issues encountered when localising a software have to do with the users' flexibility to themselves change the interface. If the software has the ability for the user to rename fields in order to - for example - call a "project" a "job" or name a "client" a "customer", you would want this change to take effect throughout the company. Rather than changing the client interface on each single workstation, a commonly used option is to change those details in the data base to which every workstation logs on. The result of this setup is a mixture of where field names and program names come from. The "Select" in "Select Client" or "Select Job" would come from the local software whilst the words "Client" and "Job" would come from the data base to allow for companies to have a "Select Customer" or a "Select Project". The localisation for another language will therefore involve translation of the word "Select" as part of the software and the word "Client" as part of a standard database for that language (that may then be further amended by the end user).

Whereas this solution will work fine where the localised integrated project management system is only used in one and the same language, it will create additional snags if users of different languages need access to the same data. If for example group companies in different countries use the same job costing system and need to be able to access each others data or if the company's headquarter needs access to audit the data of the group companies you might need to log-on with an English client software into a Portuguese data base ending up with a mixture of languages in program- and field-names.

There are different approaches thinkable to resolve those issues:

First and Easiest - take away the flexibility of the users to make changes to the terminology of their system and base it all in the local installation

Pro:
-quick and easy to implement
-foolproof
-easy cross-language access

Contra:
-reduction of flexibility means reduction of user acceptance and conceived user-friendliness

Second - store all terminology in multiple languages both of data records as well as programs in the data base and only keep the executable on the local workstation with the executable giving a choice which language to use

Pro:
-relatively easy to implement
-easy cross-language access
-full flexibility is retained

Contra:
-increase of data traffic will most certainly affect the speed of all functions

Third - store all terminology both for data records as well as programs in the local installation with a choice to use the preset terminology, the user defined terminology or a different language

Contra:
-most long winded to implement

Pro:
-full flexibility retained
-speed not affected
-fully multilingual

This last option is most certainly the optimal choice when introducing multilingual functionality and working on the localisation of an integrated job costing system. If there is then an option to distribute terminology changes to all workstations via the data base, giving the user the option to update their software, when they log on to the data base or keep their default and in addition an option to revert to the preset settings, both flexibility and user acceptance as well as multilingual functionality are guaranteed.

Annex: This article has only covered some of the basic multilingual difficulties encountered when localising a project management software for other countries. It is therefore not meant to give a complete synopsis of every aspect of multilingual interoperability. Two of these aspects not considered, that would constitute even greater challenges to be overcome are 'Grammar' and 'Writing not based on the latin alphabet': If the software not only has program commands consisting of nouns, e.g. "Client Creation" or infinitive noun combinations, e.g. "Enter Job number", but more complex sentences, e.g. "Click here to open client entry screen", grammar in different languages would have to be considered. If the software needed to be localised for the e.g. Arab, Hebrew or Chinese language and writing, a whole lot of additional hurdles would need to be overcome.

© 2008 Volker Bendel - Volker Bendel is manager of the training department of Agency Software Worldwide, the producers of the "Paprika/Rebus" job costing software (http://www.paprika-software.com and http://www.rebus-software.com). Originally from a legal background, he has several years experience in planning and implementing Job Costing and Accounting Software Systems in the Creative Industry. He has also delivered training courses in the UK, Europe, Dubai, the US, China and Australia. Prior to that he worked as a senior business consultant in Hong Kong and as a department manager of a design department in Hong Kong

Article Source: http://EzineArticles.com/?expert=Volker_Bendel

By Volker Bendel

Technical Writing - A Checklist For a Software Document Writing Project

Here is a general check list that you might find useful to make sure your software documentation project does not miss anything:

-Do you have access to the software project's Scope Document?
-Do you have access to the functional and marketing specs of the software project?
-Have you written a Documentation Plan for this project?
-Is your Documentation Plan approved by the client or the authorized project manager?
-Do you know who will review the document?
-Do you have an approved Template for this project?
-Do you know where you'll get your image and/or multi-media files from?
-Do you have an official Style Guideline that you'll follow?
-Will there be any single-sourced collaterals (like a help file, or a different-sized version of the same document) compiled from the same source file?
-Will you need any hardware to complete the project?
-Will you need to travel to other locations to gather information for the project?
-Will you need to interview any Subject Matter Experts to complete the project?
-Will you need to participate in or arrange any teleconferences or webinars to gather information or report about the project?
-What version management platform will you use for document version control? (MS SourceSafe? Agile?)
-How will you backup your files?
-Will you write the document alone or will there be other technical writers on the project?
-Will there be any in-house peer review required before you submit the document to official management review?
-Will the end product be localized and translated to other languages?
-Do you need to follow any special guidelines for localization?
-Will you have any access to a tracker system to incorporate the results of bug reports?
-Will you need to compile any training materials/sets from the source files?

If you take the necessary measures and precautions ahead of time depending on the answers to these questions you'll have a more successful documentation performance.

If you are interested to read more about what technical writing is all about and how it can help you earn a steady living, visit http://www.learntechnicalwriting.com. You might be pleasantly surprised with what you'll find out. Join the thousands who are already helped and inspired by this information provided by a Fortune 500 Senior Technical Writer. Visit today and claim your free report "How Much Do Technical Writers Make?"

Article Source: http://EzineArticles.com/?expert=Ugur_Akinci

By Ugur Akinci Platinum Quality Author

Rabu, 18 Maret 2009

Team Project Management Software

Buying the right team project management software for your office is not always easy. You want to make sure that the project management software you purchase will cover all of our management needs. In this article I will highlight some key questions to consider before purchasing the project management software.

You will first need to decide what type of software you actually require. Can your team suffice with low end team project management software, the mid-level products, or is it essential for your team to have the high-end software in order to succeed?

The low end software products can be used from an online host at a minimal fee. Mid-level software management software will be more expensive and range from $2,000 to well over $20,000. Your high end software is generally $50k and up. Remember though, you get what you pay for. If you have a small team you will usually only require a low end product. Larger companies will of course require the mid to higher end software.

You will want to buy software that is flexible to your ever changing need. Generally the software you purchase will be used for your company for an extended period of time. Over time your business needs will change and you will need software that is able to adapt to the ever changing needs.

Some other things to consider before purchasing software is how the software performs scheduling, the platform the solution is built on, can the product separate your project teams, will it be able to offer one click Microsoft Project imports and exports, can it make templates easily, can the navigation be changed, does it offer numerous reports that can be shared or customized, does the software support four task relationships, and is the solution customizable.

Buying team project management software can be a large investment for your business. Make sure you are purchasing the right product level for your sized company and make sure you are getting the product that offers the most for your needs at an affordable rate.

Additional Resources

Task project management software

Project Management System Software

Article Source: http://EzineArticles.com/?expert=George_Christodoulou

By George Christodoulou Platinum Quality Author

Is Project Management Software the Way Forward?

There has never been a time where a foot forward in business has been more vital. Efficiency is most certainly the key to maintaining a successful business, and through the use of IT solutions, project management, a key component in business, can be made easy.

It is cost-effective and hassle free to have Project Management software designed specifically for your business, and it will make a significant difference to your business needs.

Off the shelf Project Management software is, of course a cheaper alternative but may not fit every single need for your company and that is why bespoke software, made to fit your business is an option that many companies have been investing in.

Project Accounting packages help eliminate those processing repetitions that waste resources and slow down business operations. Conversely, some processes can be lost through inefficient management systems, so Project Management software aims to improve efficiency throughout the entire business, synching all departments.

Poor performing companies almost always communicate poorly from department to department, and this is largely due to having to use so many different software packages. Data either gets lost or forgotten about.

But with a single software system that allows you to time record, plan and invoice, this eliminates the need to duplicate data, which saves time and also safeguards information.

Tight integration within your accounts department will eliminate the possibility of over spending, thus improving the performance of your company. Also electronic data is more environmentally friendly and saves on paper costs. This may sound trivial from a financial point of view but a reduction in such sundries as paper over time can make a difference, especially during a time of economic downturn.

Integrated systems allow a project plan to have its own task lists, calendar and messaging service which simplifies the organisation of a project, so employees understand their role on a particular project and everything is recorded, through a simple to use system.
These systems can be integrated through an existing intranet also which will aid a company's transition from existing software packages. There really are many ways that Project Management software can benefit your business.

Companies may not be willing to splash out on such an expense given the current recession, but if it is clear that business is stalling and not running as smooth as you would like, then more efficient IT solutions would be able to improve business efficiency almost instantaneously, which in the long term would benefit the key areas of your business.

Software development has moved at a frantic pace. It seems only a short while ago that companies would save vital information onto floppy disks that would be couriered over to other departments. We are now in an age where we have the technology to implement quick, efficient and safe methods of information transfer, so why complicate matters?

Unify your database, accounts and diary into one, easy to use package and watch the performance of your company improve. By all means, search for off the shelf software packages that will suit your business, but for the best way to improve performance, Project Management software built to your business's specification will make an immediate impact, ask any manager or CEO using an integrated system and they will echo this. The technology is there, so why not embrace it?

Shaun Parker is a leading business expert with many years of experience in the IT industry. Find out more about project management software at http://www.e1business.com

Article Source: http://EzineArticles.com/?expert=Shaun_Parker

By Shaun Parker Platinum Quality Author